For the construction of the roundabout with a diameter of 22m, land had to be acquired on the uphill side and a retaining wall up to 4m high with noise protection elements had to be built. The retaining wall was founded using micropiles.
In the area of the retaining wall, the gas and water pipes were renewed.
As part of the roundabout construction, the street lighting was adapted.